法兰连接火炬塔架整体吊装有限元校核
Numerical Simulation on Integral Hoisting for Flare Stack with Flange Connection Structure
DOI: 10.12677/MOS.2017.61002, PDF, HTML, XML, 下载: 1,544  浏览: 3,804 
作者: 葛兵, 张宏志, 刘传:大庆油田工程建设有限公司安装公司,黑龙江 大庆;盛选禹:清华大学核能与新能源技术研究院,北京;徐雅晨:清华大学天津高端装备研究院先进能源装备技术研究所,天津
关键词: 法兰连接火炬塔架整体吊装CATIA有限元分析加固Flange Connection Flare Stack Integral Hoisting CATIA Finite-Element-Analysis Strengthen
摘要: 法兰连接结构火炬塔架一般采用分节吊装,本文提出一种法兰连接结构火炬塔架整体吊装技术方法的创新。利用CATIA对火炬塔架整体进行100%实体建模,使用CATIA有限元分析模拟火炬塔架整体吊装时的水平和竖直两个极限状态工况,对吊装时塔架的强度和稳定性进行校核计算,查找出危险点及提出薄弱结构的加固处理措施,为吊装工艺设计和方案制定提供依据。
Abstract: Segmentation hoisting is generally used for flare stack with flange connection structure. This paper presents a technical innovation of integral hoisting of flare stack with flange connection struc- ture. In the paper, CATIA finite-element-analysis is used to build 100% model of flare stack and to simulate working condition in both horizontal and vertical limit states. During the integral hoisting of flare stack, strength and stability of flare stack during hoisting are checked and calculated. Dangerous points are found. Measures of strengthening weak structure are proposed and reference is provided for hoisting procedure design and formulation of hoisting plan.
文章引用:葛兵, 盛选禹, 张宏志, 刘传, 徐雅晨. 法兰连接火炬塔架整体吊装有限元校核[J]. 建模与仿真, 2017, 6(1): 10-20. https://doi.org/10.12677/MOS.2017.61002

参考文献

[1] SH/T 3029-2014石油化工排气筒和火炬塔架设计规范[M]. 北京: 中华人民共和国工业和信息化部, 2014.
[2] 盛选禹, 唐守琴, 编. CATIA有限元分析命令详解与实例[M]. 北京: 机械工业出版社, 2005.