黄河源区班多水库的短期优化调度研究
Short-Term Optimal Operation of Banduo Reservoir in the Source of Yellow River
DOI: 10.12677/JWRR.2017.61004, PDF, HTML, XML, 下载: 1,773  浏览: 3,751  国家自然科学基金支持
作者: 王晓宇, 白 涛, 畅建霞:西安理工大学,西北旱区生态水利工程国家重点实验室,陕西 西安;白 钰:黄河上游水电开发有限责任公司,青海 西宁
关键词: 短期优化调度发电量最大遗传算法班多水电站Short-Term Optimal Operation Maximal Power Generation Genetic Algorithm Banduo Hydropower
摘要: 针对黄河源区班多水库尚缺乏指导其运行的具体的调度方案,且存在防凌期库面易结冰、丰水期有大量弃水、枯水期发电量急剧下降等问题,本文对班多水库分别建立了不同典型日、周调度的短期定出力常规调度模型和发电量最大优化调度模型,采用遗传算法求解优化调度模型。通过对比常规与优化的日、周调度中发电量、弃水及出力等结果,短期优化调度减少了弃水量,增加了发电量;获得了班多水库初步运行方式,揭示了班多水库的最优运行规律。研究发现:班多水库的周调度较日调度结果更为理想,具有周调节潜力。研究成果可用于指导班多水电站不同时期的运行调度,可提高水资源利用效率和发电企业的经济效益。
Abstract: Banduo reservoir, located in the source area of the Yellow River, is lack of specific operation schemes. There are many problems such as the freezing of the reservoir surface during the ice prevention period, the large amount of abandoned water in flood season and the drastic decrease of the power generation in dry season. In this paper, the short-term conventional operation model of constant output and the operation model of maximal power generation optimized by the genetic algorithm were established under daily and weekly periods. By comparing the power generation, abandoned water and output in different periods, it is found that the short-term optimal operation reduces the amount of abandoned water and increases the power generation. Initial operation mode of Banduo reservoir is obtained and optimal operation rules are derived. Banduo reservoir has the potential of weekly operation since the weekly results are better than the daily’s. This study can guide the actual operation of Banduo hydropower station in different periods, which can improve water resources utilization and economic benefit of power generation enterprises.
文章引用:王晓宇, 白涛, 白钰, 畅建霞. 黄河源区班多水库的短期优化调度研究[J]. 水资源研究, 2017, 6(1): 24-32. https://doi.org/10.12677/JWRR.2017.61004

参考文献

[1] 丁学林. 经济运行方式在班多、苏只水库调度中的应用[J]. 青海电力, 2012(S2): 45-47, 51. DING Xuelin. Application of economical operation mode in regulation of the Banduo and Suzhi reservoirs. Qinghai Electric Power, 2012(S2): 45-47, 51. (in Chinese)
[2] JALALI, M. R., AFSHAR, A. and MARINO, M. A. Multi-colony ant algorithm for continuous multi-reservoir operation optimization problem. Water Resources Management, 2007, 21(9): 1429-1447.
[3] 陈立华, 梅亚东, 董雅洁, 等. 改进遗传算法及其在水库群优化调度中的应用[J]. 水利学报, 2008(5): 550-556. CHEN Lihua, MEI Yadong, DONG Yajie, et al. Improved genetic algorithm and its application in optimal dispatch of cascade reservoirs. Journal of Hydraulic Engineering, 2008(5): 550-556. (in Chinese)
[4] 朱彦刚. 白石水库调度方案探析[J]. 东北水利水电, 2016(3): 36-39, 71. ZHU Yangang. Discussion on dispatching scheme of Baishi reservoir. Water Resources & Hydropower of Northeast China, 2016(3): 36-39, 71. (in Chinese)
[5] 马跃先, 于健, 李生俊, 等. 黄河上游梯级水库防凌优化调度方案研究[J]. 人民黄河, 2012(2): 4-6. MA Yuexian, YU Jian, LI Shengjun, et al. Optimal operation schemes of cascade reservoirs in the Upper Reaches of the Yellow River for preventing ice jam. Yellow River, 2012(2): 4-6. (in Chinese)
[6] 靳少波, 沈延青. 黄河上游梯级电站水库联合调度方式探讨[J]. 电网与清洁能源, 2014(2): 98-100. JIN Shaobo, SHEN Yanqing. Discussions on the joint scheduling mode for the reservoirs of cascade hydropower stations in the Upper Reaches of the Yellow River. Power System and Clean Energy, 2014(2): 98-100. (in Chinese)
[7] 金文婷, 黄强. 龙羊峡和刘家峡梯级水电站水库调水调沙合理库容研究[J]. 水利水电快报, 2015(4): 38-41. JIN Wenting, HUANG Qiang. Study on reasonable storage in water-sediment regulation of Longyangxia and Liujiaxia cas-caded hydro-plant reservoirs. Express Water Resources & Hydropower Information, 2015(4): 38-41. (in Chinese)
[8] 白夏, 戚晓明, 汪艳芳. 黄河上游梯级水库多目标水沙联合模拟优化调度模型[J]. 人民珠江, 2016(10): 12-17. BAI Xia, QI Xiaoming and WANG Yanfang. Multi-objective joint simulation and optimization operation model of water and sediment for cascade reservoirs in the Upper Yellow River. Pearl River, 2016(10): 12-17. (in Chinese)
[9] 周之豪. 水利水能规划[M]. 第2版. 北京: 中国水利水电出版社, 1999. ZHOU Zhihao. Water resources and hydropower planning. 2nd Edition. Beijing: China Water Conservancy and Hydropower Press, 1999. (in Chinese)
[10] 邓胜权. 山区日调节小水电站水能计算[J]. 水电与新能源, 2015(11): 36-39. DENG Shengquan. Hydropower energy calculation for small daily regulation hydropower stations in mountainous areas. Hydropower and New Energy, 2015(11): 36-39. (in Chinese)
[11] 宋臻. 关于黄河上游水电开发的若干构想[J]. 西北水电, 2001(3): 7-10, 73. SONG Zhen. Thoughts on hydropower development of the Upper Yellow River. Northwest Water Power, 2001(3): 7-10, 73. (in Chinese)
[12] 畅建霞, 黄强, 田峰巍. 黄河上游梯级电站补偿效益研究[J]. 水力发电学报, 2002(4): 11-17. CHANG Jianxia, HUANG Qiang and TIAN Wei’e. Study on compensation benefits of cascade hydroelectric power stations on Yellow River Upstream. Journal of Hydroelectric Engineering, 2002(4): 11-17. (in Chinese)
[13] 王天宇, 董增川, 付晓花, 等. 黄河上游梯级水库防洪联合调度研究[J]. 人民黄河, 2016(2): 40-44. WANG Tianyu, DONG Zengchuan, FU Xiaohua, et al. Research on Upper Yellow River cascaded reservoirs in flood control operation. Yellow River, 2016(2): 40-44. (in Chinese)
[14] 李雪梅, 王玲, 林银平, 等. 龙刘水库调节对黄河上游汛期水量变化的影响[J]. 人民黄河, 2008(11): 65-66. LI Xuemei, WANG Ling, LIN Yinping, et al. Influences of Longyangxia and Liujiaxia reservoirs regulation on water change in flood season of Upper Yellow River. Yellow River, 2008(11): 65-66. (in Chinese)
[15] 李五勤, 吴成国, 王义民, 等. 基于风险分析的刘家峡水库最优防凌库容配置方案研究[J]. 水力发电学报, 2013(6): 76-82. LI Wuqin, WU Chengguo, WANG Yimin, et al. Study on optimal allocation scheme for ice control capacity of Liujiaxia reservoir based on risk analysis. Journal of Hydroelectric Engineering, 2013(6): 76-82. (in Chinese)
[16] 张太祥, 许栋, 初云鹏. 班多水电站调速器事故配压阀的设计与应用[J]. 液压气动与密封, 2013(10): 9-11. ZHANG Taixiang, XU Dong and CHU Yunpeng. The design and application of emergency distributing valve for Banduo hydropower plant governor system. Hydraulics Pneumatics & Seals, 2013(10): 9-11. (in Chinese)