地铁建设中的接口管理与优化研究
Research on Interface Management and Optimization in Subway Construction
DOI: 10.12677/MSE.2016.54017, PDF, HTML, XML, 下载: 1,953  浏览: 3,469 
作者: 杨国伟:上海轨道交通十三号线发展有限公司,上海;曹杰, 张小宁:同济大学经济与管理学院,上海
关键词: 地铁质量屋接口管理里程碑管理Subway HoQ Interface Management Milestone Management
摘要: 地铁建设管理中接口问题普遍存在,本文利用质量屋模型找出地铁建设过程中接口管理的关键措施,用PBS分解规划接口管理的具体工作,并应用里程碑管理的理念去优化管理接口,确保工程的功能实现和按期完成,降低项目的整体风险,并以上海在建的地铁13号线为例,验证上述措施的有效性。
Abstract: The interface problems in the management of metro construction commonly exist. This paper uses the house of quality model to find out the key measures of interface management and the PBS to introduce the specific work and apply the milestone management philosophy to optimize the interface management, which ensures the functions realized and the engineering completed on schedule and reduce the overall risk of the project. And at the end of the article, it takes the construction of Metro Line 13 in Shanghai as an example to verify the effectiveness of the above measures.
文章引用:杨国伟, 曹杰, 张小宁. 地铁建设中的接口管理与优化研究[J]. 管理科学与工程, 2016, 5(4): 157-166. http://dx.doi.org/10.12677/MSE.2016.54017

参考文献

[1] 上海市统计局. 上海统计年鉴[M]. 北京: 中国统计出版社, 2014.
[2] 中华人民共和国国家统计局. 中国统计年鉴[M]. 北京: 中国统计出版社, 2014.
[3] 李蒙. 数字轨道交通工程的设备接口管理[D]: [硕士学位论文]. 华中科技大学, 2006.
[4] Chan, W.T., Chen, C., Messner, J.I., et al. (2005) Interface Management for China’s Build-Operate-Transfer Projects. Journal of Construction Engineering & Management, 131, 645-655.
https://doi.org/10.1061/(ASCE)0733-9364(2005)131:6(645)
[5] Chua, D.K. and Godinot, M. (2006) Use of a WBS Matrix to Improve Interface Management in Projects. Journal of Construction Engineering & Management, 132, 67-79.
https://doi.org/10.1061/(ASCE)0733-9364(2006)132:1(67)
[6] 乐云, 崇丹, 蒋卫平. 大型复杂群体项目分解结构(PBS)概念与方法研究[J]. 项目管理技术, 2010(2): 39-43.
[7] 郭杰. 城市轨道交通工程接口管理研究[D]: [硕士学位论文]. 北京: 中国铁道科学研究院, 2011.
[8] Ju, Q.Q. and Ding, L.Y. (2015) A Web-Based System for Interface Management of Metro Equipment Engineering. Journal of Intelligent & Robotic Systems, 79, 577-590.
https://doi.org/10.1007/s10846-014-0121-y
[9] 蔡荧. 浅论香港地铁的里程碑管理[J]. 现代企业文化, 2009(21): 76-77.
[10] Alhammad, A.M. (2000) Common Interface Problems among Various Construction Parties. Journal of Performance of Constructed Facilities, 14, 71-74.
https://doi.org/10.1061/(ASCE)0887-3828(2000)14:2(71)