钢结构预制装配式变电站接地系统研究
Study on Grounding System of Steel Structure Fabricated Substation
DOI: 10.12677/JEE.2016.44030, PDF, HTML, XML, 下载: 1,544  浏览: 3,434 
作者: 靳 静:上海电力设计院有限公司,上海
关键词: 预制装配式变电站防雷接地Steel Structure Fabricated Substation Lightning Protection Ground Connection
摘要: 预制装配式变电站通过工厂预制和现场安装两个阶段建设,因其建设周期较传统变电站得到明显缩短,更加适应了电网建设步伐,逐渐成为城市变电站推崇的建设方式。接地网作为变电站设备接地及防雷保护接地系统,对安全运行起着重要的作用。钢结构预制式变电站对于变电站的接地系统设计提供了新的理念,为优化设计方案、节约接地材料提供了条件。本文以上海兴邦110 kV变电站为例,研究钢结构预制装配式变电站的接地系统,阐述该方案的优势。
Abstract: Through the two stages of construction of factory prefabrication and site installation, fabricated substation is becoming more and more respected city substation construction side because it can accelerate construction schedule of power grid. Grounding System is important for safe operation, because it is the lightning protection of the substation and the ground connection of electrical equipments. Steel structure Fabricated Substation has offered new idea for optimizing design and saving material. Taking Shanghai Xingbang 110 kV substation as an example, this paper has completed the research of grounding system of steel structure fabricated substation and elaborated the advantage of this system.
文章引用:靳静. 钢结构预制装配式变电站接地系统研究[J]. 电气工程, 2016, 4(4): 232-238. http://dx.doi.org/10.12677/JEE.2016.44030

参考文献

[1] 柳国良, 张新育, 胡兆明. 变电站模块化建设研究综述[J]. 电网技术, 2008, 32(14): 36-38.
[2] 高美金, 傅旭华. 标准配送式变电站的特点与建设[J]. 浙江电力, 2014(3): 31-34.
[3] 王慎全. 预制装配式变电站[J]. 农村电气化, 2008(11): 45-46.
[4] GB 50057-2010. 建筑物防雷设计规范[S]. 北京: 中国计划出版社, 2013.
[5] GB 50065-2011. 交流电气装置的接地设计规范[S]. 北京: 中国计划出版社, 2011.
[6] 李玉山, 贺宝珍, 裴永. 变电站接地网设计研究[J]. 水利水电工程, 2014, 4(34): 69-71.
[7] 孙燕, 张琴. 变电站接地网选用铜覆钢绞线的设计与分析[J]. 电力与能源, 2014, 35(3): 314-320.
[8] 黄昌威, 安韵竹. 变电站接地网不同接地材料接地特性研究[J]. 陕西电力, 2014, 42(11): 9-12.