时间影响分析法在工期索赔管理中的应用
Application of Time Impact Analysis in Time Extension Claim Management
DOI: 10.12677/JOGT.2021.433038, PDF,  被引量   
作者: 侯进才:中国石油管道局工程有限公司国际事业部,河北 廊坊
关键词: 工期索赔时间影响分析法索赔报告案例Time Extension Claim Time Impact Analysis Claim Report Claim Case
摘要: 文章针对目前常用的工期影响分析方法命名不统一的问题,引入了美国造价工程师协会(AACE)层级命名分类系统,规范各工期分析方法的名称;然后详细介绍了时间影响分析法的步骤,并应用实例进一步阐述了撰写工期分析报告的具体过程,旨在为计划工程师进行工期延误分析提供参考。
Abstract: This paper points out the issue of non-uniform nomenclature for the commonly used method of pro- ject schedule analysis, and presents the hierarchical nomenclature classification system published by American Institute of Cost Engineers (AACE) to standardize the names of each analysis method. Then detailed steps of time impact analysis are explained, and the specific structure of drafting time claim report is further illustrated with a claim case, in order to provide reference for planning engineers to conduct time extension claim.
文章引用:侯进才. 时间影响分析法在工期索赔管理中的应用[J]. 石油天然气学报, 2021, 43(3): 107-117. https://doi.org/10.12677/JOGT.2021.433038

参考文献

[1] 牛永宏, 于东温. 国际工程合同管理程序指南[M]. 北京: 中国建筑工业出版社, 2010: 120-125.
[2] 曹吉鸣. 项目进度规划与控制原理[M]. 北京: 科学出版社, 2013: 270-273.
[3] Society of Construction Law. Delay and Disruption Protocol. https://www.scl.org.uk/