基于UMM的主设备运维策略研究
Research on Operation and Maintenance Decision-Making of Main Equipment Based on UMM
摘要:
介绍了目前南网运维策略现状,并分析了现在运维策略中存在的弊端。针对此,本文提出了一种考虑设备全寿命周期成本,基于贝叶斯网络模型的不确定多阶段多目标运维决策模型,并给出了模型求解过程。最后通过建立GIS的UMM (uncertainty)运维策略模型,制定最佳的运维策略,验证所提出UMM决策模型的有效性。
Abstract: In this paper the existing situation of the operation maintenance strategy of gird main equipment is presented and the problems of traditional operation maintenance strategy are analyzed. A new model based on uncertainty multi- stage and multi-object by Bayesian network is presented in this paper, which is for making operation maintenance strategy with the consideration of life cycle cost. In the end a GIS example proves the UMM model’s practical applications.
参考文献
[1]
|
马奔正, 黄宵宁, 葛乐, 等 (2010) .无人值守变电站最优运维策略的分析与建模. 电力系统及其自动化学报, 22, 83-87.
|
[2]
|
章健, 张弛, 蒋声婴, 等 (2012) .基于LCC的配电站设备检修策略研究. 华东电力, 40, 1576-1579.
|
[3]
|
李俭川, 胡茑庆, 秦国军, 等 (2003) .贝叶斯网络理论及其在设备故障诊断中的应用. 中国机械工程, 14, 896-899.
|
[4]
|
殷可, 郁东升, 李莉华, 等 (2009) .LCC方法评价500 kV变压器的研究与应用. 华东电力, 37, 1916-1917.
|
[5]
|
黄良宝, 马则良, 张建平, 等 (2007) .考虑LCC管理的电网规划方案评价研究. 华东电力, 37, 91-94.
|