预制装配式220 kV终端变电站典型设计研究
Study on Typical Design of Fabricated 220 kV Terminal Substation
DOI: 10.12677/JEE.2016.43017, PDF, HTML, XML, 下载: 2,762  浏览: 5,495 
作者: 靳 静:上海电力设计院有限公司,上海
关键词: 预制装配式变电站土建先行通用接口通用基础设计Fabricated Substation Civil Work First General Base General Interface Design
摘要: 随着电网建设进度的加快,如何缩短变电站的建设周期显得日益重要。预制装配式变电站通过工厂预制和现场安装两个阶段建设,越来越成为城市变电站推崇的建设方式。另外,以往必须先确定设备再进行设计,从而再进行施工安装的流程成为了必须打破的瓶颈。本设计方案主要研究预制装配式变电站内的主要设备的通用基础,可在设备订货前就按通用基础、通用接口予以设计,实现土建先行,从而达到加快工程建设速度的目的。
Abstract: With the accelerated construction schedule of power grid, how to cut construction period of substation is an increasingly important issue. Through the two stages of construction of factory prefabrication and site installation, fabricated substation is becoming more and more respected city substation construction side. Moreover, we must design after determining devices firstly, and then is civil work and equipment installation. Now we must break the bottleneck of this traditional mode. The main research of this design scheme is the general base of electrical equipments in fabricated substation. In accordance with the general base and general interface, we can design before equipment ordering and realize civil work first, so as to achieve the purpose of speeding up the pace of substation construction.
文章引用:靳静. 预制装配式220 kV终端变电站典型设计研究[J]. 电气工程, 2016, 4(3): 133-140. http://dx.doi.org/10.12677/JEE.2016.43017

参考文献

[1] 柳国良, 张新育, 胡兆明. 变电站模块化建设研究综述[J]. 电网技术, 2008, 32(14): 36-38.
[2] 高美金, 傅旭华. 标准配送式变电站的特点与建设[J]. 浙江电力, 2014(3): 31-34.
[3] 国家电网公司基建部. 国家电网公司“两型一化”试点变电站建设技术导则[S]. 北京: 国家电网公司基建部, 2007.
[4] 国家电网公司. 国家电网公司220 kV变电站典型设计推荐方案[S]. 北京: 国家电网公司, 2007.
[5] 王少晖, 李绍星, 柳国良. 模块化变电站的建设模式及其经济性能比较[J]. 电气技术, 2012(2): 77-81.
[6] 张冰松. 模块化变电站工程的精细化管理[J]. 电力与能源, 2011(6): 522-523.
[7] 王慎全. 预制装配式变电站[J]. 农村电气化, 2008(11): 45-46.