工期紧迫型单位工程进度计划编制方法讨论
Discussion on the Method of Preparing the Schedule of a Time-Limited Unit Project
摘要:
工程建设项目周期长、环节多,质量、成本、工期三大目标相互制约,如何在保证质量的前提下缩短工期、降低建设成本成为编制施工组织设计的关键。流水施工通过合理的规划,统筹工程建设的三大目标,成为了工期紧迫型单位工程编制进度计划的重要手段。本文结合淮阴卫校1号实训楼特点,分析了流水施工缩短工期要点,探讨如何运用流水施工理论来编制工期紧迫型单位工程进度计划。
Abstract:
Construction projects have the features of long duration and multiple links. Three objections, quality, cost and schedule, are mutually restrictive. How to shorten the construction period and reduce construction cost under the premise of guaranteeing quality is key to construction organization design. The flow construction integrated these three objectives by proper planning, and it has become an important means of preparing the schedule of a project time limited. This paper taking the first training building in Huaiyin Medical School, analyzed the key points of shortening the construction period. In the end, we discussed how to apply the theory of flow construction to prepare the schedule of a time-limited unit project.
参考文献
[1]
|
李建成. 施工项目中的进度计划与控制研究[D]: [硕士学位论文]. 上海: 上海交通大学, 2007.
|
[2]
|
卢乃荪. 单位工程施工进度计划中施工过程的合理安排[J]. 企业技术开发, 2011, 30(7): 178-179, 195.
|
[3]
|
黄汉澄. 建筑工程施工现场的流水施工[J]. 中国科技财富, 2009(8): 34.
|
[4]
|
陈清树, 周霞. 建筑工程施工组织设计中流水施工形式的确定[J]. 泸州职业技术学院学报, 2012(2): 63-67.
|
[5]
|
张新华, 范建洲. 建筑施工组织设计[M]. 北京: 中国水利水电出版社, 2008: 60-80.
|
[6]
|
李冰利. 建筑工程项目施工工期与资源配置研究[D]: [硕士学位论文]. 北京: 清华大学, 2009.
|