Power-V + 扭力冲击器组合在X井的试验研究
The Experimental Study of Power-V + Torsional Percussion Drilling Tool Combination in Well X
摘要:
X井首次使用了Power-V + 扭力冲击器钻具组合新技术,效果明显,井斜控制在0.2˚左右,钻速平均3.69 m/h,钻速是邻井S井钻速的1.26倍,节约钻井周期6~7 d以上。该技术的成功应用,为库车山前大北区块在吉迪克组和苏维依组的钻井提速提供了有力的实践依据。
Abstract:
Well X has tried the new technology Power-V + Torsional Percussion Drilling Tool Combination which was first used in Well X, the effect of application was obvious. The well deviation was con-trolled at about 0.2 degrees and the average drilling speed was 3.69 m/h, which was 1.26 times of Well S. It saves more than 6 - 7 days of drilling cycle. The successful application of this new technology provides a strong practical basis for increasing drilling speed in Kuqa Piedmont block in Jidike Formation and Suweiyi Formation.
参考文献
|
[1]
|
李玮, 李卓伦, 刘伟卿, 等. 扭转冲击提速工具在文安区块的现场应用[J]. 特种油气藏, 2016, 23(4): 144-146.
|
|
[2]
|
马升武, 张金斌, 张瑞英, 等. 扭力冲击器在玉北地区应用研究[J]. 钻采工艺, 2013, 36(4):37-39.
|
|
[3]
|
周祥林, 张金成, 张东清. TorkBuster扭力冲击器在元坝地区的试验应用[J]. 钻采工艺, 2011, 34(2): 15-17.
|
|
[4]
|
张克勤. 元坝地区钻井难题分析与技术对策探讨[J]. 石油钻探技术, 2010, 38(3): 27-30.
|