摘要:
由于受地层条件等诸因素的影响,自钻式锚杆抗拔力达不到设计要求的情况时有出现。如何提高自钻式锚杆抗拔力是采用自钻式锚杆支护时必须考虑的一个重要问题。以承德钢厂烧结机改造工程5#边坡(VK0 + 226.94-K0 + 270.64)支护为例,介绍了影响自钻式锚杆抗拔力的因素,主要从钻进成孔工艺、清孔方法、钻进技术参数选择、注浆控制等方面论述了提高自钻式锚杆抗拔力的技术措施。
Abstract: Due to the influence of the geological conditions and other factors, pullout resistance of self-drilling anchor can’t achieve the design requirements appearing from time to time. How to improve the self-drilling anchor pullout resistance is an important question that must be considered in the self-drilling anchor supporting. Take Chengde Steel sintering machine renovation project of No.5 slope (VK0 + 226.94-K0 + 270.64) supporting as an example, describing the factors that affecting the self-drilling anchor pullout resistance, discussing technical measures to improve the self- drilling anchor pullout resistance mainly from drilling into the hole process, hole cleaning method, drilling technology parameter selection, grouting control and so on.
参考文献
[1]
|
程良奎, 范景伦, 韩军. 岩土锚固[M]. 北京: 中国建筑工业出版社, 2003.
|
[2]
|
胡海军, 李正聪, 李文榕. 上仰锚索及自钻式锚杆在边坡加固中的应用[J]. 探矿工程(岩土钻掘工程), 2005, 32(z1): 134- 135.
|
[3]
|
李旭, 王世顺, 谢在巍. 自钻式锚杆在基坑支护中的应用[J]. 铁道建筑, 2006, 5: 65-66.
|
[4]
|
朱瑞晨, 黄熠辉. 自钻式锚杆在洛古水电站崩坡积体支护中的应用[J]. 浙江水利科技, 2009, 6: 20-21.
|
[5]
|
苗晓雯, 李惠琴, 崇六喜. 自钻式锚杆的设计应用[J]. 路基工程, 2003, 6: 73-75.
|