基于窗口时间影响分析法的海外土建工程工期索赔研究——以阿曼某项目为例
Study on Schedule Claims for Overseas Civil Construction Projects Based on Windowed Time Impact Analysis—A Case Study in Oman
摘要: 随着我国工程建设企业拓展海外市场,工期管理与索赔成为项目成效关键。本文以阿曼某土建项目为例,采用窗口时间影响分析法分析工期延误及责任划分。研究显示,该方法可清晰量化延误事件对总工期的影响,为承包商工期索赔提供依据,并降低违约风险。本文提出管理优化建议,为海外项目工期索赔提供参考。
Abstract: With Chinese contractors expanding overseas, schedule management and delay claims are critical. This paper analyzes a civil construction project in Oman using Windowed Time Impact Analysis (TIA + WTI) to assess delays and responsibility allocation. Results show the method quantifies delay impacts and supports contractors’ claims while mitigating liquidated damages risk. Management recommendations are provided for overseas projects.
参考文献
|
[1]
|
李东旗. EPC工程全周期总承包商索赔管理研究——以巴基斯坦电站项目为例[D]: [博士学位论文]. 威海: 山东大学), 2021.
|
|
[2]
|
王竹琳, 张水波. 工期延误分析方法的国际研究动态[J]. 工程管理学报, 2011, 25(6): 601-605.
|
|
[3]
|
Society of Construction Law (2017) Delay and Disruption Protocol (2nd Edition), Society of Construction Law.
|
|
[4]
|
AACE International (2011) Recommended Practice No. 29R-03: Forensic Schedule Analysis. AACE International.
|
|
[5]
|
Braimah, N. (2013) Construction Delay Analysis Techniques—A Review of Application Issues and Improvement Needs. Buildings, 3, 506-531.
|
|
[6]
|
Hegazy, S. (2012) Delay Analysis Methodology in UAE Construction Projects. PM World Journal, 1, 1-21.
|