地铁施工危险源辨识研究——以宁波地铁三号线为例
Hazard Identification in Metro Construction—Case Study of Ningbo Metro Line 3
DOI: 10.12677/HJCE.2019.83057, PDF,    科研立项经费支持
作者: 罗宗保:宁波市城建设计研究院有限公司,浙江 宁波;刘仲武:中国铁道科学研究院集团有限公司城市轨道交通中心,北京;陈音圻, 郑圣坡, 吴 萍, 徐亦冬:浙江大学宁波理工学院,浙江 宁波
关键词: 危险源辨识地铁施工LEC评价法风险接受准则宁波Hazard Identification Metro Construction LEC Evaluation Method Risk Acceptance Criteria Ningbo
摘要: 宁波计划于2021年前开通5条地铁,将进入大地铁时代。但宁波作为沿海城市,其特殊的软土地质加上高地下水位,也给地铁的建设带来各种安全隐患。因此,通过辨识危险源来减少施工危险事故的发生就变得尤为重要。本研究通过整理和完善已有研究成果,形成适用于宁波地区的地铁施工危险源辨识库。从宁波地铁三号线着手,通过分析其先天条件、施工工艺以及相关安全管理架构等,初步形成施工危险源检查表。再通过与宁波地铁三号线施工方、监理方等有多年管理经验的专家讨论议定该项目相对重要的几项施工危险源。最后引入LEC评价法和风险接受准则,对于施工危险源进行半定量的打分,从而辨识出项目的重大危险源。通过本研究方法,可以针对不同的施工项目确定其存在的危害程度大的危险源,从而在开工前采取相应的预防管控措施,来减少工程事故的发生。
Abstract: Ningbo plans to operate five metro lines in 2021, hence entering the era of Big Metro. However, as a coastal city, Ningbo's special soft soil feature plus the high groundwater level bring various safety hazards to the construction of the metro system. Therefore, it is particularly important to reduce the occurrence of construction hazards by identifying sources of danger. This study compiles and improves the existing research results to form a dangerous source identification library for metro construction in Ningbo. Starting from Ningbo Metro Line 3, through the analysis of its innate conditions, construction technology and related safety management structure, a construction hazard source checklist was initially formed. Then, experts are interviewed such as the construction and supervision parties of Ningbo Metro Line 3; several construction hazards relatively important for the project were discussed. Finally, the LEC evaluation method and risk acceptance criteria were introduced to semi-quantitatively identify the construction hazard sources to identify major hazards of the project. Through this research method, it is possible to determine the hazard source with a large degree of hazard for different construction projects, in order to take corresponding preventive management and control measures before the start of construction to reduce the occurrence of engineering accidents.
文章引用:罗宗保, 刘仲武, 陈音圻, 郑圣坡, 吴萍, 徐亦冬. 地铁施工危险源辨识研究——以宁波地铁三号线为例[J]. 土木工程, 2019, 8(3): 484-493. https://doi.org/10.12677/HJCE.2019.83057

参考文献

[1] 钟春玲, 夏彦杰. 地铁施工安全的影响因素分析[J]. 吉林建筑工程学院学报, 2014, 31(2): 11-14.
[2] 张秋福. 郑州地铁工程项目施工安全管理研究[D]: [硕士学位论文]. 南京: 南京理工大学, 2011.
[3] 许志国. 地铁车站土建工程施工管理中的风险与对策[J]. 技术研发, 2017(12): 216.
[4] 郭健, 钱劲斗. 地铁车站深基坑施工风险识别与评价[J]. 土木工程与管理学, 2017(9): 33-37.
[5] 苟敏, 赵金先. 基于ISM模型的地铁盾构施工风险分析[J]. 沈阳建筑大学学报: 社会科学版, 2014(10): 391-393.
[6] 赵艳莉. 建筑施工安全管理中的危险源评价及管理方法分析[J]. 建筑, 2014(11): 63-64.
[7] 张思戬. 地铁安全施工风险因素综合评价分析研究[D]: [硕士学位论文]. 西安: 西安理工大学, 2018.
[8] 赵衍发. 浅埋暗挖法下穿既有地铁车站的风险控制[D]: [博士学位论文]. 北京: 北京交通大学, 2013.