浅析锚固法兰施工中的质量管理
The Anchor Flange Quality Management during the Construction
摘要: 锚固法兰施工,涉及到焊接、防腐、机械、土建及混凝土、钢筋施工。涉及的专业多,周期长。为更好地进行锚固法兰施工,结合本项目实际,对施工过程的质量管理进行探讨和剖析。
Abstract: Anchor flange construction, involves welding, anti-corrosion, machinery, civil engineering and concrete, and reinforcement construction. It involves many processes and has a long cycle. In order to better carry out anchor flange construction, combined with the actual situation of the project, the quality management of the construction process is discussed and analyzed.
文章引用:段维超, 刘晓亮, 关沂山, 李莹. 浅析锚固法兰施工中的质量管理[J]. 石油天然气学报, 2020, 42(4): 192-202. https://doi.org/10.12677/JOGT.2020.424131

参考文献

[1] GB 50369-2014油气长输管道工程施工及验收规范[S]. 北京: 中国计划出版社, 2014.
[2] SAES-L-440 Anchors for Buried Pipelines [S]. 沙特阿美规范, July 2017.
[3] 沙特北部管道程序文件. CPP-NGCP-CM-PRO-0003_1 Procedure for Concrete Works 2020 [Z].
[4] 沙特北部管道程序文件. SATIP-H-003-01 Coating Application on Concrete Surfaces 2020 [Z].
[5] 沙特北部管道程序文件. CPP-NGCP-CM-MS-0011 Method Statement for Temporary Cathodic Protection Installation 2020 [Z].
[6] SATIP-A-114-01 Earthwork—Site Preparation, Excavation and Backfill during Construction [S]. 沙特阿美规范, July 2017.