长距离深埋隧洞TBM拆机研究
Research on Dismantling of TBM in Long-Distance and Deep-Buried Tunnel
DOI: 10.12677/HJCE.2021.104040, PDF,   
作者: 马 骋:新疆伊河开发建设管理局,新疆 乌鲁木齐
关键词: TBM拆机方案比选“拆 + 埋”法TBM Dismantling Plan Comparison and Selection “Dismantling + Burying” Method
摘要: 本文结合新疆某隧洞工程施工实例,对长距离深埋隧洞TBM拆机方案提出了拆卸洞室前置法与“拆 + 埋”法,从地质、工程安全、投资、工期进行分析研究,最终采用“拆 + 埋”法实现TBM拆机,以期对长距离深埋隧洞TBM拆机施工提供借鉴,从而达到快速、安全、经济的目的。
Abstract: Based on a construction example of a tunnel project in Xinjiang, this paper proposes the pre-demolition method and the “demolition + burying” method for the TBM dismantling plan of a long-distance deep-buried tunnel. The analysis and research are carried out from the perspective of geology, engineering safety, investment, and construction period. Finally, the “dismantling + burying” method is adopted to realize the TBM dismantling, in order to provide a reference for the TBM dismantling construction of long-distance deep-buried tunnels, so as to achieve the purpose of rapid, safe and economical.
文章引用:马骋. 长距离深埋隧洞TBM拆机研究[J]. 土木工程, 2021, 10(4): 356-360. https://doi.org/10.12677/HJCE.2021.104040

参考文献

[1] 李世民. 大型敞开式TBM长大隧洞内无损拆机技术[J]. 云南水力发电, 2019, 35(5): 126-128, 135.
[2] 黄金光. TBM拆卸洞及拆机起重系统优化设计研究[J]. 隧道建设, 2017, 37(2): 242-249.
[3] 肖海晖, 郭荣伟. TBM洞内拆卸方案[J]. 山西建筑, 2010, 36(3): 362-363.
[4] 冯欢欢, 陈馈. 西秦岭隧道洞内拆机方案设计与探讨[J]. 铁道工程学报, 2016(3): 87-92.
[5] 宋卿. 双护盾TBM洞内拆机施工组织及方法[J]. 冶金丛刊, 2018(14): 251-252.