软岩深埋地铁车站初支拱盖法施工WBS-RBS-AHP风险评估
WBS-RBS-AHP Risk Assessment of Deep-Buried Soft Rock Subway Station Construction with Primary Support Arch-Cover Method
DOI: 10.12677/HJCE.2021.105049, PDF,   
作者: 付铁军:重庆市轨道交通(集团)有限公司,重庆;张照秉:重庆潼南高新技术产业开发区管理委员会,重庆;张晨阳*:重庆大学土木工程学院,重庆
关键词: 地铁车站初支拱盖法风险评估WBS-RBS层次分析法Subway Station Primary Support Arch-Cover Method Risk Assessment WBS-RBS Analytic Hierarchy Process
摘要: 文章依托重庆轨道交通九号线一期工程红岩村车站,采用WBS-RBS风险耦合识别技术对红岩村车站初支拱盖法施工进行了风险识别,得到了施工过程中的23个风险源,而后采用AHP分析法对识别出的风险源进行风险评估,找出风险权重较大的风险源,为针对性的风险控制和深入研究指明了方向,同时也证明了该方法在工程实际中的有效性,能够为地铁车站初支拱盖法施工提供科学、实用的理论指导。
Abstract: This paper is based on Hongyancun Station of Chongqing Rail Transit Line 9 phase I project. WBS-RBS risk identification technology is utilized to identify the risks of the construction of Hongyancun Station with Primary Support Arch-Cover Method, and 23 risk sources during the construction process are obtained. Then, Analytic Hierarchy Process (AHP) is utilized to perform risk assessment on the identified risk sources, to find out the risk sources with larger weight. It points out the direction for specific risk-controlling and in-depth research. And the effectiveness of this method in engineering practice is also proved, which can provide scientific and practical theoretical guidance for construction of subway station with Primary Support Arch-Cover Method.
文章引用:付铁军, 张照秉, 张晨阳. 软岩深埋地铁车站初支拱盖法施工WBS-RBS-AHP风险评估[J]. 土木工程, 2021, 10(5): 428-438. https://doi.org/10.12677/HJCE.2021.105049

参考文献

[1] 薛洪松. A地铁暗挖车站工程施工阶段安全风险管理研究[D]: [硕士学位论文]. 兰州: 兰州交通大学, 2017.
[2] 杜宪武, 刘运思, 牟天光. PBA地铁车站及暗挖区间隧道施工风险评估[J]. 工程建设与设计, 2019(19): 167-168+176.
[3] 王路杰. 浅埋暗挖地铁车站施工风险评价研究[D]: [硕士学位论文]. 青岛: 山东科技大学, 2017.
[4] 王䶮, 刘保国, 亓轶. 基于WBS-RBS与故障树耦合的地铁施工风险与评价[J]. 地下空间与工程学报, 2015, 11(S2): 772-779.
[5] 李晓兵. 双侧壁导坑法地铁车站开挖施工安全风险管理研究[D]: [硕士学位论文]. 兰州: 兰州交通大学, 2018.