基于全寿命周期成本模型的输变电设备检修策略研究
Study on the Maintenance Strategies of Transmission and Transformation Equipment Based on Life Cycle Cost Model
摘要: 当前电力设备检修策略制定过程中未考虑全寿命周期成本(Life Cycle Cost, LCC)因素,存在着检修策略无法实现经济效益最大化的问题。本文以定期检修和状态维修为例,基于全寿命周期成本模型修正了常用的输变电设备检修策略。在保证系统安全稳定运行的前提下,制定出合理的检修策略,同时实现经济性的目标,具有工程实用性。
Abstract: The factor of LCC (Life Cycle Cost) is not considered in the present process of making maintenance strategy for power equipment, which leads to the failure of the maintenance strategy to maximize the economic benefits. In this paper, these common maintenance strategies for transmission and transformation equipment are corrected based on the LCC model considering time based mainte-nances and condition based maintenance. On the premise of ensuring the safe and stable operation of the system, some reasonable maintenance strategies of highly valuable in engineering are formulated, and the economic goal is realized.
文章引用:李昭廷. 基于全寿命周期成本模型的输变电设备检修策略研究[J]. 电力与能源进展, 2017, 5(6): 158-162. https://doi.org/10.12677/AEPE.2017.56024

参考文献

[1] 郭丽杰. 基于风险的石化动设备智能维修决策研究[D]: [博士学位论文]. 北京: 化工大学, 2009.
[2] 王丹, 邢丽敏. 变电站设备状态检修技术及其应用探讨[J]. 科技创新导报, 2011(30): 76.
[3] Nilsson, J. and Bertling, L. (2007) Maintenance Management of Wind Power Systems Using Condition Monitoring Systems-Life Cycle Cost Analysis for Two Case Studies. IEEE Transactions on Energy Conversion, 22, 223-229.
[4] 滕乐天, 陈红兵, 王怡风. LCC在设备采购中的应用实践[J]. 华东电力, 2007, 35(10): 27-29.
[5] 苏海锋, 张建华, 梁志瑞, 等. 基于LCC管理的高压直流输电线路工程设计方案评价研究[J]. 华东电力, 2011(5): 698-701.
[6] 郭基伟, 柳纲, 唐国庆, 王英. 电力设备检修策略的马尔可夫决策[J]. 电力系统及其自动化学报, 2004(16): 6-10.
[7] 张大波. 基于状态监测与系统风险评估的电力设备维修及更新策略研究[D]: [博士学位论文]. 重庆: 重庆大学, 2012.
[8] 许婧, 王晶, 高峰, 等. 电力设备状态检修技术研究综述[J]. 电网技术, 2000, 24(8): 48-52.
[9] 宋秀省. 电力设备状态检修技术研究[J]. 低碳世界, 2013(16): 66-67.
[10] 李刚, 于长海, 刘云鹏, 等. 电力变压器故障预测与健康管理: 挑战与展望[J]. 电力系统自动化, 2017: 1-12.
[11] 冀凯琳. 基于LCC理论的电力设备检修策略研究[D]: [硕士学位论文]. 北京: 华北电力大学(北京), 2011.