CPR1000核电厂凝结水系统管道水锤效应研究
Analysis of Water Hammer in Condensate Extraction System of CPR1000 Nuclear Power Plant
摘要: 针对CPR1000核电厂凝结水抽取系统喷淋阀闭合产生水锤的问题,利用FLOWMASTER一维流体软件与CEASAR II管道应力分析软件结合的时程分析方法计算阀门关闭时产生的水锤力。对某核电厂凝结水抽取系统关闭喷淋阀时产生的水锤力进行计算,根据计算结果在阀门所在管线相应位置增加支架,保证管线强度在阀门开关时满足要求,同时大幅降低管线振动现象,形成该类核电厂管道水锤问题的通用计算方法。
Abstract: For solving the problem of water hammer caused by condensate spray valves closing in the deaerator extraction system of CPR1000 nuclear power plant, the water hammer force is calculated by the time-history analysis method combined with FLOWMASTER one-dimensional fluid software and CEASAR II pipeline stress analysis software. According to the calculation results of water hammer force during condensate spray valve closing, we increase the support in the corresponding position of the valve pipeline to ensure that the strength of the pipeline meets the requirements when the valve is on and off, and at the same time greatly reduce the vibration phenomenon of the pipeline. Then this kind of nuclear power plant pipe water hammer general calculation method has been summed up.
文章引用:孔祥永, 赖诚, 白金川, 刘玉紫, 徐樟楠, 袁亮. CPR1000核电厂凝结水系统管道水锤效应研究[J]. 核科学与技术, 2018, 6(4): 124-131. https://doi.org/10.12677/NST.2018.64015

参考文献

[1] 胡晓阳. 基于Flowmaster的泵站系统水力过渡过程研究[D]: [硕士学位论文]. 成都: 西华大学, 2012.
[2] 张正楼, 张献娟, 刘玉璐. 基于Flowmaster的核电站循环冷却水系统泵出口阀关闭规律优化研究[J]. 给水排水, 2015, 51(2): 121-124.
[3] 杨勇, 沈良洁. 常规岛给水系统瞬态分析研究[J]. 产业与科技论坛, 2017, 16(18): 49-52.
[4] 王鑫, 韩伟实. 压水堆核电厂主给水管道水锤计算及分析[J]. 原子能科学技术, 2010, 44(S1): 192-197.
[5] 赵嘉明. 核动力装置一回路水锤研究及仿真计算[D]: [硕士学位论文]. 哈尔滨: 哈尔滨工程大学, 2008.
[6] 广东核电培训中心, 编. 900MW压水堆核电站系统与设备[M]. 北京: 原子能出版社, 2005.